Skip to main content
Access IndiaPLATFORM
HomeHSNChapter 85HSN 8506 90 00

Parts

Parts of primary cells and primary batteries (dry cell components)

BIS QCO APPLICABLE · ISI MARK SCHEME · IS 8144 · CPCB OVERLAY

HSN 8506 90 00 (parts of primary cells and primary batteries) is covered by a Bureau of Indian Standards Quality Control Order. Conformity to IS 8144:2018 is mandatory under the ISI Mark Scheme, with the Steel and Steel Products Quality Control Order 2024 (S.O. 3716(E)) imposing an additional input-material standard-mark requirement on tin plate and tin-free steel components. Extended Producer Responsibility authorisation under the Battery Waste Management Rules and the E-Waste (Management) Rules apply as separate customs-clearance overlays.

What this is
HSN code
8506 90 00
Chapter
85 · Electrical machinery and equipment and parts thereof
BIS QCO
Applicable · ISI Mark Scheme · CM/L required
Indian Standard
IS 8144 · effective 25-05-1987
Applicable Partner Government Agencies
BISBIS·Bureau of Indian Standards
CPCBCPCB·Central Pollution Control Board

Procedural directions for customs clearance are issued by: Central Board of Indirect Taxes and Customs.

Compliance steps
  1. 1
    Source only from a Bureau of Indian Standards CM/L-licensed manufacturer holding a current licence against IS 8144:2018. Verify the supplier's CM/L number, licensed product scope, and manufacturing facility on the BIS online register before placing the purchase order.
    IS 8144:2018 · S.O. 516(E) dated 25-05-1987 · BIS (Conformity Assessment) Regulations, 2018
  2. 2
    Where the parts are fabricated from tin plate or tin-free steel (Schedule 2, serial numbers 3–7 of the Steel and Steel Products QCO), confirm the input material itself bears the BIS standard mark per Schedule 1 serial numbers 108–109. The consignment must be accompanied by the input-material test certificate.
    Steel and Steel Products Quality Control Order, 2024 · S.O. 3716(E) dated 29-08-2024 · Scheme-I of Schedule-II to the BIS (Conformity Assessment) Regulations, 2018
  3. 3
    Ensure each part bears the ISI mark and the supplier's CM/L number in accordance with Scheme-I of Schedule-II to the BIS (Conformity Assessment) Regulations, 2018. Marking must appear on the product itself; packaging-only marking is not sufficient.
    BIS (Conformity Assessment) Regulations, 2018 · F.No. BS/11/11/2018 dated 04-06-2018
  4. 4
    Obtain Extended Producer Responsibility authorisation from the Central Pollution Control Board under the Battery Waste Management Rules before import. Verify compliance with the Battery Waste Management (Amendment) Rules, 2023. Micro enterprises as defined under the MSMED Act, 2006 are exempt from the E-Waste EPR requirement.
    S.O. 3984(E) dated 22-08-2022 · S.O. 4669(E) dated 25-10-2023 · E-Waste (Management) Rules, 2022 · G.S.R. 801(E) dated 02-11-2022
  5. 5
    If the steel input material is imported without a BIS licence or certification, apply through the TCQCO portal for clarification on each such steel consignment as mandated by the Ministry of Steel circular dated 20-10-2023. Ensure compliance with CBIC clarification F.No. 401/88/2023-CUS.III dated 09-11-2023 on that circular.
    Ministry of Steel circular F.No. S-20011/14/2021-Tech dated 20-10-2023 · CBIC clarification F.No. 401/88/2023-CUS.III dated 09-11-2023
A word of counsel

The most common error on this tariff line is treating the finished-part BIS CM/L obligation under IS 8144:2018 as the only compliance hook, while overlooking that the steel input materials used to fabricate those parts — tin plate and tin-free steel — independently require BIS standard-mark certification under the Steel and Steel Products QCO 2024. Customs has authority to detain a consignment where the test certificate for the input material is absent, even when the finished part itself carries a valid ISI mark; importers who delegate input-material compliance entirely to the overseas supplier without documentary verification are the ones most frequently caught at port.

Need a regulatory steer on this product?
Speak to a regulatory counsel about your specific HSN, IS, and supplier situation.
Speak to an Expert
Frequently asked
Does HSN 8506 90 00 require BIS certification?
Yes. Parts of primary cells and primary batteries require conformity to IS 8144:2018 under the ISI Mark Scheme; import is permitted only from manufacturers holding a current BIS CM/L licence covering the specific parts and manufacturing facility.
Is Extended Producer Responsibility authorisation required separately from BIS QCO compliance?
Yes. EPR authorisation under the Battery Waste Management Rules (S.O. 3984(E)) and, where applicable, the E-Waste (Management) Rules, 2022 is independent of BIS QCO compliance. Micro enterprises as defined under the MSMED Act, 2006 are exempt from the E-Waste EPR requirement.
Does the Steel and Steel Products QCO 2024 apply to battery parts made from tin plate or tin-free steel?
Yes. Per S.O. 3716(E) dated 29-08-2024, battery parts specified in Schedule 2 (serial numbers 3–7) fabricated from tin plate or tin-free steel must use BIS-standard-marked input material; the consignment must be accompanied by the input-material test certificate.
Does a single CM/L licence cover all part types and manufacturing facilities?
No. The CM/L licence is scope-specific by part type, specification, and manufacturing facility; parts outside the licensed scope or from an unlicensed plant are not covered and are liable to detention at port.
Last verified against gazette notifications: 2026-05-18. Source: BIS / CPCB / CBIC / Indian Customs CUSDATA.
Related