Of square or rectangular- cross-section
Welded square and rectangular hollow section tubes of iron or steel
HSN 7306 61 00 (welded square and rectangular hollow section tubes of iron or steel) is covered by a Bureau of Indian Standards Quality Control Order. Conformity to the Indian Standard mapped in Schedule 1 of the Steel and Steel Products Quality Control Order, 2024 is mandatory under the ISI Mark Scheme by virtue of S.O. 3716(E) dated 29 August 2024. Steel Import Monitoring System (SIMS) registration administered by the Directorate General of Foreign Trade applies as a separate customs-clearance overlay.
Procedural directions for customs clearance are issued by: Central Board of Indirect Taxes and Customs, Directorate General of Foreign Trade.
- 1Verify the foreign manufacturer holds a current BIS CM/L licence against the Indian Standard specified in Schedule 1 of the Steel and Steel Products Quality Control Order, 2024 for this product category. Confirm the licensed scope covers the hollow section dimensions and facility of manufacture before placing the purchase order.Steel and Steel Products Quality Control Order, 2024 · S.O. 3716(E) dated 29-08-2024 · ISI Mark Scheme under Scheme-I of Schedule-II to the BIS (Conformity Assessment) Regulations, 2018
- 2Ensure the consignment is accompanied by two test certificates: one for the finished hollow section itself (Schedule 2, serial number 2) and one bearing the BIS standard mark for the stainless steel input material, issued by the BIS-certified input manufacturer.Steel and Steel Products Quality Control Order, 2024 · S.O. 3716(E) dated 29-08-2024 · Schedule 2 and Schedule 1 requirements
- 3Register the consignment on the SIMS portal not earlier than 60 days before the expected arrival date, paying the ₹500 registration fee. The automatic registration number is valid for 75 days; confirm it remains within validity on the date of arrival.DGFT Notification 33/2015-20 dated 28-09-2020 · DGFT Notification 28/2023 dated 28-08-2023
- 4Ensure strict compliance with CBIC Instruction 16/25-CUS dated 18-06-2025 as modified by CBIC Instruction 23/25-CUS dated 15-07-2025 regarding the Indian Standard of the respective input material of steel products intended for import as notified and mapped in the QCO, and requiring mandatory SIMS portal registration.CBIC Instruction 16/25-CUS dated 18-06-2025 · CBIC Instruction 23/25-CUS dated 15-07-2025
- 5If the consignment does not carry BIS certification, apply for and obtain clarification on the TCQCO portal before arrival. Quote the BIS CM/L number, SIMS registration number, and both test certificates on the bill of entry; any one absent or scope-mismatched triggers consignment detention.Ministry of Steel Circular dated 20-10-2023 vide F.No.S-20011/14/2021-Tech · CBIC clarification F.No.401/88/2023-CUS.III dated 09-11-2023
The most frequent compliance failure on this tariff line is treating the finished-product CM/L as the sole documentation requirement while overlooking the mandatory dual test-certificate obligation — one for the hollow section and one for the BIS-marked input material. Customs officers check both certificates independently at port; arrival with only the finished-product certificate, or with an input-material certificate from a non-BIS-certified mill, results in consignment detention regardless of the validity of the finished-product CM/L licence. Confirm input-material BIS certification in the supplier's mill test reports at order stage, not at port.